Parliament Workbench
Data: Motions & questions to 3 Dec 2026

Written Question · S6W-10554 · Session 6

What the combined generating capacity in GW will be of the projects that it anticipates will be constructed under the ScotWind leasing roun…

Answered Asked by Liam Kerr Con Lodged 22 Aug 2022

The question

To ask the Scottish Government what the combined generating capacity in GW will be of the projects that it anticipates will be constructed under the ScotWind leasing round; whether it remains of the view, set out in its 2020 Sectoral Marine Plan for Offshore Wind Energy, that "...an overall national limit on generating capacity of 10GW was required as a mitigation measure”, and what the total actual investments in the Scottish supply chain will be, in light of the Cabinet Secretary for Net Zero, Energy and Transport's reported statement in January 2022 that ScotWind "will secure investment in the Scottish supply chain of at least £1 billion for every GW of power".

The answer

Answered by Michael Matheson on 21 Sep 2022 · 30 days after it was lodged, on time

Following the clearing announcement on the 22 August 2022, the ScotWindleasing round has identified 20 offshore wind projects with a potential overall capacity of 27.6GW. Based on the Supply Chain Development Statements (SCDS) submitted with the leasing applications, developers have committed to invest around £1.4bn per project.
Before construction, these projects will go through project development and consenting processes, respond to geographical and technological requirements, and find a route to market. For this reason, it is not possible to have a clear indication at this time of what will be constructed and the combined generating capacity.
The Sectoral Marine Plan for Offshore Wind Energy (SMP-OWE) assessed a potential generation figure of 10GW and therefore does not comment on additional generation or impacts. The SMP-OWEis subject to an Iterative Plan Review (IPR) process, which allows Scottish Government to review the conclusions of the Plan against new available information. Through the IPR process we will consider the impacts of the new potential generation figure of 27.6GW.

In the Official Report

No contribution in the Official Report cites S6W-10554 by reference.