Further to the answer to question S6W-07089 by Mairi Gougeon on 15 March 2022, whether it can provide an update on how much funding (a) it …

Answered Asked by Donald Cameron Con Lodged 19 Jul 2022

The question

To ask the Scottish Government, further to the answer to question S6W-07089 by Mairi Gougeon on 15 March 2022, whether it can provide an update on how much funding (a) it allocated to and (b) was distributed to successful grant applicants from the Croft House Grant scheme in (a) 2021-22 and (b) 2022-23.

The answer

Answered by Mairi Gougeon on 18 Aug 2022 · 30 days after it was lodged, on time

Financial Year
Budget Allocation
Actual Grant Paid (£)
2021-22
£1.9m
924,060.30
2022-23
*
£1.9m
160,505.95
* As at 1 August 2022Funding under the Croft House Grant is provided retrospectively in up to three stages. For this reason, funding committed in any financial year can be claimed by applicants and paid in both the current and following two to three financial years.A high proportion of house builds are being delayed due to material and labour supply issues, which has resulted in fewer claims being submitted in 2021-22 and in the early part of 2022-23.No CHG application has been refused due to a lack of budget.