Parliament Workbench
Data: Motions & questions to 3 Dec 2026

Written Question · S6W-09604 · Session 6

Further to the answer to question S6W-02233 by Graeme Dey on 10 September 2021, whether it will provide an update on how many times since J…

Answered Asked by Craig Hoy Con Lodged 30 Jun 2022

The question

To ask the Scottish Government, further to the answer to question S6W-02233 by Graeme Dey on 10 September 2021, whether it will provide an update on how many times since January 2019 train services between North Berwick and Edinburgh Waverley have been cancelled for (a) all and (b) part of its journey due to (i) track problems, including signalling and flooding, and (ii) track congestion.

The answer

Answered by Jenny Gilruth on 2 Aug 2022 · 33 days after it was lodged, on time

ScotRail advise that between 6 January 2019 [the start of 2018-19: reporting period 11] and 25 June 2022 [the end of 2022-23: reporting period 3], there were 340 full cancellations and 95 part-cancellations on the North Berwick lines as a result of infrastructure issues. As the member will know, Rail Infrastructure is a reserved matter.
While full or part-cancellation as a result of track congestion are not reported separately, ScotRail also advise that there were a further 41 full cancellations and 35 part-cancellations to ScotRail services as a result of the actions of other train operating companies.

In the Official Report

No contribution in the Official Report cites S6W-09604 by reference.