Written Question · S6W-09346 · Session 6

Further to the answer to question S6W-08743 by Jenny Gilruth on 14 June 2022, whether it will provide the information requested regarding w…

Answered Asked by Liam Kerr Con Lodged 19 Jun 2022

The question

To ask the Scottish Government, further to the answer to question S6W-08743 by Jenny Gilruth on 14 June 2022, whether it will provide the information requested regarding when it will replace the 25 Class 43 HSTs in the ScotRail fleet; whether it will confirm whether Transport Scotland's position remains that such replacement will occur only when "Network Rail has completed the electrification of all or most of the routes they serve", as reported in The Herald on 21 May 2022; when it anticipates that "the electrification of all or most of the routes they serve" will be completed, and for what reason it did not provide this information in its answer.

The answer

Answered by Jenny Gilruth on 25 Jul 2022 · 36 days after it was lodged, on time

The replacement of train fleets in Scotland, including the HSTs, is aligned with the phases of the Decarbonisation Action Plan, a link to which is provided here:- Rail Services Decarbonisation Action Plan | Transport Scotland
This timescale is of course subject to continuous review in line with delivering the decarbonisation of the rail network in Scotland affordably and practicably and any other relevant developments, including recommendations arising from the Steering Groups considering the recommendations of, and subsequent analysis from the recent RAIB report into the Carmont accident.

In the Official Report

No contribution in the Official Report cites S6W-09346 by reference.