Further to the answer to question S6W-08724 by Michael Matheson on 7 June 2022, whether it will provide the timeframe for when a decision o…

Answered Asked by Alexander Burnett Con Lodged 7 Jun 2022

The question

To ask the Scottish Government, further to the answer to question S6W-08724 by Michael Matheson on 7 June 2022, whether it will provide the timeframe for when a decision on whether to grant planning approval for Fetteresso Wind Farm, case reference WIN-110-1, will be made.

The answer

Answered by Michael Matheson on 28 Jun 2022 · 21 days after it was lodged, on time

Scottish Ministers received the Public Inquiry Report on 18 February 2022 and are currently considering the terms of the report. The timeframe for considering reports, in addition to considering all other material considerations and application documents is very much site specific. The determination for Fetteresso is currently progressing in line with the most recent average timescales. 10 determinations, where a Public Inquiry was held, have been issued since January 2021. The average time taken, between receipt of the Public Inquiry Report from the Planning and Environmental Appeals Division (the “DPEA”) and the issue of these determinations, is around 6 months within a range of 2 to 15 months.

In the Official Report