Written Question · S6W-09077 · Session 6

Further to the answer to question S6W-07277 by Humza Yousaf on 1 April 2022, what decisions have been made by NHS Scotland Assure since 1 J…

Answered Asked by Miles Briggs Con Lodged 6 Jun 2022

The question

To ask the Scottish Government, further to the answer to question S6W-07277 by Humza Yousaf on 1 April 2022, what decisions have been made by NHS Scotland Assure since 1 June 2021.

The answer

Answered by Humza Yousaf on 26 Jul 2022 · 50 days after it was lodged, 32 days after it was due

NHS Scotland Assure has carried out twenty Key Stage Assurance Reviews (KSARs) since it was established. At the conclusion of the KSAR, NHS Assure advises whether it supports or does not support a project. Where a project is not supported, an action plan is prepared by the responsible Health Board with support from NHS Scotland Assure to address the issues identified. The project can subsequently be reassessed. Twelve of the twenty KSARs resulted in a “supported” decision and eight resulted in a “not supported” decision and work is underway to address the issues identified. Responsibility for approving business cases continues to lie with the Scottish Government.
NHS Scotland Assure has so far supported the following projects at the full business case stage:
Project Name
Elective Orthopaedic Centre (National Treatment Centre),
Kirkcaldy Victoria Hospital
National Treatment Centre
- Phase, NHS Golden Jubilee
The ANCHOR Centre
The Baird Family Hospital
North East Health Hub (Parkhead)
Inverness Campus NTC

In the Official Report

No contribution in the Official Report cites S6W-09077 by reference.