Further to the answer to question S6W-07060 by Shona Robison on 17 March 2022, what the key stages are of assessment, and how many properti…

Answered Asked by Mark Griffin Lab Lodged 26 Apr 2022

The question

To ask the Scottish Government, further to the answer to question S6W-07060 by Shona Robison on 17 March 2022, what the key stages are of assessment, and how many properties are at each stage of assessment.

The answer

Answered by Shona Robison on 12 May 2022 · 16 days after it was lodged, on time

Single Building Assessment applicants are supported through the process to complete the application form and commission professional services ahead of receiving the final survey report. 15 pilot blocks are within the Application Phase. 10 pilot blocks are within the Delivery Phase. One additional block is existing within the new approach where we direct commission those professional services on behalf of a building.