Further to the answer to question S6W-05100 by Humza Yousaf on 5 January 2022, whether it has received (a) six-month and (b) 12-month progr…

Answered Asked by Alex Cole-Hamilton LD Lodged 25 Mar 2022

The question

To ask the Scottish Government, further to the answer to question S6W-05100 by Humza Yousaf on 5 January 2022, whether it has received (a) six-month and (b) 12-month progress reports for the nine research projects on long COVID.

The answer

Answered by Humza Yousaf on 19 Apr 2022 · 25 days after it was lodged, on time

For reference details of the 9 projects are available from the Chief Scientist Office website
Long Covid Call – Chief Scientist Office (scot.nhs.uk)
Six-month progress reports have been received for all 9 projects
A twelve-month progress report has been received for project LTE/20/04
On 31 March 2022 the Chief Scientist Office hosted a virtual symposium where the lead investigators for each of the 9 projects presented the results obtained to date

In the Official Report

No contribution in the Official Report cites S6W-07709 by reference.