Parliament Workbench
Data: Motions & questions to 3 Dec 2026

Written Question · S6W-07448 · Session 6

Whether it is the case that work on the Housing to 2040 Improving the quality of all homes milestones for 2021-22 has not begun and, if thi…

Answered Asked by Mark Griffin Lab Lodged 15 Mar 2022

The question

To ask the Scottish Government whether it is the case that work on the Housing to 2040 Improving the quality of all homes milestones for 2021-22 has not begun and, if this is the case, (a) what the reasons are for this and (b) when work will (i) begin and (ii) be completed on the actions to (A) consult on new housing standards, (B) review the housing for varying needs design guide, (C) review the adaptations system and (D) develop joint accountability and outcomes framework.

The answer

Answered by Shona Robison on 19 Apr 2022 · 35 days after it was lodged, on time

Work to progress early milestones set out within Housing to 2040 for improving the quality of all homes is currently underway. We intend to consult on proposals for a new Housing Standard later this year, and plan to launch a formal consultation on proposals for updating the Housing for Varying Needs design guide later this spring. Work on the review of the adaptations system is also underway and is expected to conclude later in the current financial year, with work to develop a joint housing, health and social care accountability and outcomes framework scheduled to start later this year.

In the Official Report

No contribution in the Official Report cites S6W-07448 by reference.