How much time it will take to carry out the physical works to retro-fit and decarbonise all buildings in Scotland in order to meet the 2030…

Answered Asked by Dean Lockhart Con Lodged 2 Mar 2022

The question

To ask the Scottish Government how much time it will take to carry out the physical works to retro-fit and decarbonise all buildings in Scotland in order to meet the 2030 targets under its Heat in Buildings Strategy.

The answer

Answered by Patrick Harvie on 21 Mar 2022 · 19 days after it was lodged, on time

The amount of time spent on the physical works for each building retrofit can vary and depends on a range of factors. Some of the factors which influence the time taken are: the building type; the types of work needed to improve the energy efficiency of the building; and the type of zero emissions heating installed.
Our workforce assessment, currently underway, will give insight into the drivers of the range of retrofit times and related workforce and skills needs across relevant sectors. In addition, working with industry, we will co-produce a Heat in Buildings supply chain action plan focussed on ensuring industry can deliver at the pace and scale needed.

In the Official Report

No contribution in the Official Report cites S6W-07163 by reference.