Parliament Workbench
Data: Motions & questions to 3 Dec 2026

Written Question · S6W-07073 · Session 6

Whether it will provide an update on the (a) timetable for the delivery and (b) latest estimated overall cost of public money of the two ne…

Answered Asked by Dean Lockhart Con Lodged 1 Mar 2022

The question

To ask the Scottish Government whether it will provide an update on the (a) timetable for the delivery and (b) latest estimated overall cost of public money of the two new ferries being built for the CalMac fleet.

The answer

Answered by Kate Forbes on 17 Mar 2022 · 16 days after it was lodged, on time

The CEO of Ferguson Marine is preparing an update, for the Net Zero, Energy and Transport Committee, on the delivery timetable and budget for vessels 801 and 802 which will be submitted before the end of March 2022.

In the Official Report

No contribution in the Official Report cites S6W-07073 by reference.