Written Question · S6W-06326 · Session 6
Further to the answer to question S6W-05611 by Michael Matheson on 17 January 2022, whether Scottish Water expects to have undertaken all t…
The question
To ask the Scottish Government, further to the answer to question S6W-05611 by Michael Matheson on 17 January 2022, whether Scottish Water expects to have undertaken all the residual work from the 2015-21 regulatory period by the end of the 2022-23 financial year, as indicated in its 2020-21 annual report.
The answer
As set out in Scottish Water’s 2020-21 Annual Report, while thousands of projects were delivered in the 2015- 21 period there were 86 projects due by but not delivering benefits to customers at 31 March 2021. Scottish Water expects customers to be receiving the benefits of 57 of these projects by the end of the 2022-23 financial year, leaving 29 still to be completed.