The question

To ask the Scottish Government, further to the answer to question S6W-03765 by Patrick Harvie on 4 November 2021, whether it will provide an update on the funding (a) available and (b) unallocated for 2021-22.

The answer

Answered by Patrick Harvie on 2 Feb 2022 · 21 days after it was lodged, on time

The funding allocation to the E-bike Loan Fund, and unallocated funds for the financial year 2021-22 up until December 2021 is summarised in the following table.
Financial Year
Funding
Unallocated
Notes
2021-22
£3,800,000
£2,117,483
up until Dec 2021

In the Official Report

No contribution in the Official Report cites S6W-05706 by reference.