To ask the Scottish Government, further to the answer to question S6W-01683 by Jamie Hepburn on 6 August 2021, what its reasons are for not applying direct government oversight of the restoration of the Glasgow School of Art, and whether it considers the restoration as a project of national importance.
The answer
The Glasgow School of Art (GSA) is an autonomous Higher Education Institution (HEI), and as such has responsibility for its own strategic and operational decision making, including those related to the rebuilding of the Mackintosh building. The GSA has made clear its intention to rebuild the Mackintosh as a fully functioning art school, engaging fully with the local community in taking this forward.
All category A listed buildings, including the Mackintosh, are of significant cultural and historic importance to Scotland and are defined in Historic Environment Scotland (HES) guidance as buildings of “outstanding special architectural or historic interest”. HES, as the lead public body for investigating, caring for and promoting Scotland's historic environment, will continue to work with the GSA, Glasgow City Council and other interested parties on the complex issues surrounding the rebuild of the Mackintosh building.
All Scottish HEIs in receipt of public funding must comply with the terms of their Financial Memorandum with the Scottish Funding Council (SFC), and the principles of good governance set out in the Scottish Code of Good HE Governance.
The SFC continues to engage regularly with the GSA at senior management and board level on a range of issues, such as institutional governance, its plans for the delivery of high quality education, and the use of its estates for this purpose. This includes the Mackintosh and the approach the GSA is taking to inform decisions around its rebuilding.
The GSA will shortly publish the first stage of this process, the Strategic Outline Business Case (OBC), which was developed in accordance with UK and Scottish Government guidance and includes input from a range of internal and external stakeholders.
All category A listed buildings, including the Mackintosh, are of significant cultural and historic importance to Scotland and are defined in Historic Environment Scotland (HES) guidance as buildings of “outstanding special architectural or historic interest”. HES, as the lead public body for investigating, caring for and promoting Scotland's historic environment, will continue to work with the GSA, Glasgow City Council and other interested parties on the complex issues surrounding the rebuild of the Mackintosh building.
All Scottish HEIs in receipt of public funding must comply with the terms of their Financial Memorandum with the Scottish Funding Council (SFC), and the principles of good governance set out in the Scottish Code of Good HE Governance.
The SFC continues to engage regularly with the GSA at senior management and board level on a range of issues, such as institutional governance, its plans for the delivery of high quality education, and the use of its estates for this purpose. This includes the Mackintosh and the approach the GSA is taking to inform decisions around its rebuilding.