How much it estimates it will cost for a typical hard-to-treat off-gas grid home rated between EPC (Energy Performance Certificate) Bands E…

Answered Asked by Liam Kerr Con Lodged 27 Jul 2021

The question

To ask the Scottish Government how much it estimates it will cost for a typical hard-to-treat off-gas grid home rated between EPC (Energy Performance Certificate) Bands E and G to achieve EPC Band C by 2025.

The answer

Answered by Michael Matheson on 20 Aug 2021 · 24 days after it was lodged, on time

Although there is no fixed definition of what a hard to treat home is, we estimate that the average cost of upgrading an off-gas grid property with an initial EPC rating between Band E and Band G to an EPC Band C could be in the region of £17,000.
As set out in our draft Heat in Buildings Strategy, the cost for an individual dwelling can differ from this average depending on the building type, materials, existing levels of energy efficiency and type of heating systems being replaced.

In the Official Report

No contribution in the Official Report cites S6W-01910 by reference.