Written Question · S6W-01885 · Session 6
Further to the answer to question S6W-00982 by Graeme Dey on 8 July 2021, how much of the £5 million budget referred to was spent on the pl…
The question
To ask the Scottish Government, further to the answer to question S6W-00982 by Graeme Dey on 8 July 2021, how much of the £5 million budget referred to was spent on the platform extension project at Milngavie railway station; what the total cost was of the platform extension project, and where additional funds were sourced from.
The answer
Of the £5M budget available in FY 20-21, £4.8M was spent on the Milngavie platform works. The total cost of the works was £5.55M. The additional funding was provided by Scottish Ministers through funding allocated to Network Rail in Control Period 6.
In the Official Report
No contribution in the Official Report cites S6W-01885 by reference.