Written Question · S6W-00237 · Session 6
Whether it will provide an update on a solution to prevent the build-up of ice on the Queensferry Crossing.
The question
To ask the Scottish Government whether it will provide an update on a solution to prevent the build-up of ice on the Queensferry Crossing.
The answer
Ice accretion and precipitation sensors were installed on the towers and deck in 2020. Weather forecasting, bridge monitoring and traffic management procedures have been continuously improved, and the mechanism of ice accumulation specific to the Queensferry Crossing is now better understood. A working group comprising Transport Scotland, the bridge Operating Company BEAR Scotland and a number of expert consultants has been established. A number of possible solutions are under consideration in terms of their feasibility.