Whether the milestone payment scheduled for March 2021 was delivered by the GRG Alliance to the Scottish Government-controlled project acco…
The question
To ask the Scottish Government whether the milestone payment scheduled for March 2021 was delivered by the GRG Alliance to the Scottish Government-controlled project account, as reported to the Finance and Constitution Committee by the Cabinet Secretary for the Rural Economy in a letter of 11 February 2021; how much the payment was scheduled to be worth, and whether this was met in full.
The answer
Milestone payments are inter-company payments related to planned investment at the Lochaber smelter and are not payments due to the Scottish Government. No payments due from GFG Alliance companies to the Scottish Government are outstanding. For reasons of commercial confidentiality, we do not publish details of compliance with commercial contractual terms although such information may be shared in confidence with the Finance and Constitution Committee where appropriate.
In the Official Report
No contribution in the Official Report cites S6W-00172 by reference.