Written Question · S6W-00053 · Session 6
On what date it awarded the contracts for the R100 broadband programme, and when the detailed programme will be announced for the (a) Highl…
The question
To ask the Scottish Government on what date it awarded the contracts for the R100 broadband programme, and when the detailed programme will be announced for the (a) Highlands and (b) north east.
The answer
The contracts for the Central and South lots of the Reaching 100% (R100) programme were signed on 16 December 2019. Contract signature for the North lot was completed on 11 December 2020, following dismissal of a legal challenge which had delayed contract signature.
As outlined in the response to S6W-00008 on 24 May 2021, the Scottish Government provided Openreach with a finalised speed and coverage template (or SCT) for the R100 North lot contract at the end of March 2021, which covers both the Highlands and the north east of Scotland. The remodelling exercise to finalise their coverage footprint is ongoing and will be subject to rigorous review through Scottish Government governance and assurance structures, and those of Building Digital UK (BDUK). The full picture across the R100 North lot contract area is expected to be available by Summer 2021.
The roll-out of R100 build in the North lot – and the associated survey work – will be completed in phases, and build plans will be reflected in our online checker at scotlandsuperfast.com.
All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
As outlined in the response to S6W-00008 on 24 May 2021, the Scottish Government provided Openreach with a finalised speed and coverage template (or SCT) for the R100 North lot contract at the end of March 2021, which covers both the Highlands and the north east of Scotland. The remodelling exercise to finalise their coverage footprint is ongoing and will be subject to rigorous review through Scottish Government governance and assurance structures, and those of Building Digital UK (BDUK). The full picture across the R100 North lot contract area is expected to be available by Summer 2021.
The roll-out of R100 build in the North lot – and the associated survey work – will be completed in phases, and build plans will be reflected in our online checker at scotlandsuperfast.com.
All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers