When work will begin constructing the roundabouts and flyover planned for the junctions of the A737, B706 and B777.

Answered Asked by Kenneth Gibson SNP Lodged 29 Sep 2021

The question

To ask the Scottish Government when work will begin constructing the roundabouts and flyover planned for the junctions of the A737, B706 and B777.

The answer

Answered by Mairi McAllan on 7 Oct 2021

With the statutory procedures completed, Transport Scotland is progressing through the necessary governance approval procedures that require to be completed before any procurement process for the A737 Improvements at Beith project could begin. Once this process is complete, The Transport Minister will write to the member with an update on plans for delivery of the project.

In the Official Report

No contribution in the Official Report cites S6O-00268 by reference.