Whether it will provide an update on the date by which it expects the Royal Hospital for Children and Young People to be opened, and what t…

Answered Asked by Dean Lockhart Con Lodged 5 Mar 2021

The question

To ask the Scottish Government whether it will provide an update on the date by which it expects the Royal Hospital for Children and Young People to be opened, and what the latest estimate is of the total cost of the project.

The answer

Answered by Jeane Freeman on 10 Mar 2021 · 5 days after it was lodged, on time

I refer the member to the answer to question S5W-35918 on 10 March 2021. All answers to written parliamentary questions are available on the Parliament's website, the search facility for which can be found at http://www.parliament.scot/parliamentarybusiness/28877.aspx
Costs have not been finalised but we expect them to be close to the original estimate of £16 million.