Written Question · S5W-35465 · Session 5

Whether it will provide an update on the electrification projects on the (a) East Kilbride and (b) Barrhead railway line.

Answered Asked by Graham Simpson Con Lodged 22 Feb 2021

The question

To ask the Scottish Government whether it will provide an update on the electrification projects on the (a) East Kilbride and (b) Barrhead railway line.

The answer

Answered by Michael Matheson on 9 Mar 2021 · 15 days after it was lodged, on time

The recently published Strategic Transport Projects Review (STPR2 Phase 1) sets out our ambitions for accelerating economic recovery and lays the groundwork for placing inclusive, greener transport options at the heart of future investment. It specifically refers to the prioritisation of the East Kilbride and Barrhead projects.
In preparation for construction Network Rail has completed vegetation management works along the line of the route and the majority of ground and site investigations required is almost complete.
Design and development work is already well advanced and contractors, SPL, will shortly begin on-site activities in the south Glasgow area (between Muirhouse South Junction and Busby Junction). This will include piling and the construction of steelwork foundations to support the future electrification works.
These enhancements will have a transformative effect on the railway and will deliver wide-ranging passenger benefits.