Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S5W-34928 · Session 5

When the CalMac vessels that are beyond their 25-year life expectancy will be replaced, and when the replacement vessels will be in operati…

Answered Asked by Jamie Greene Con Lodged 3 Feb 2021

The question

To ask the Scottish Government when the CalMac vessels that are beyond their 25-year life expectancy will be replaced, and when the replacement vessels will be in operation.

The answer

Answered by Paul Wheelhouse on 11 Feb 2021 · 8 days after it was lodged, on time

Preparatory work is underway on our next Vessel Replacement and Deployment Plan and, as set out in the Programme for Government 2020-21, we will consult on and ultimately finalise a long-term plan and investment programme for vessels and ports as part of the Islands Connectivity Plan, by the end of 2022.
Our Infrastructure Investment Plan, published on 4 February 2021, allocated a total of £580 million on ferries investment over the next 5 years. We are currently engaging with our stakeholders on specific proposals for vessel renewal on a number of routes.

In the Official Report

No contribution in the Official Report cites S5W-34928 by reference.