Written Question · S5W-34146 · Session 5
Further to the statement by the Minister for Energy, Connectivity and the Islands in its press release of 14 December 2020 on superfast bro…
The question
To ask the Scottish Government, further to the statement by the Minister for Energy, Connectivity and the Islands in its press release of 14 December 2020 on superfast broadband for homes and businesses in the north, that “more than 80% of the build we are funding will provide full fibre to the premises and speeds of up to one Gigabit per second”, how many premises will be excluded from this level of provision; in which communities these premises are located, and what capacity and broadband speeds will be provided in these cases.
The answer
At contract signature, BT indicated that they would build to almost 71,000 of the 90,530 premises that were in scope. Of these, BT have indicated that they planned to build to 60,700 as Fibre to the Premises (FTTP) or 85.6% of their build. This is an excellent outcome, delivering up to gigabit per second speeds to all benefitting from FTTP, and and, in addition, just over 10,500 premises were flagged as due to be connected via Fibre to the Cabinet (FTTC) rather than FTTP under the North lot contract.
R100 set out to ensure that everyone could access at least superfast speeds (30 Megabits per second) and so delivery of such a high proportion of full fibre (FTTP) technology is delivering more than our original commitment. As outlined in my response to S5W-30420, we have issued BT with an updated intervention area taking account of changes in commercial roll-out plans and so we expect that this FTTC figure will change once roll-out plans are finalised.
Once this remodelling work is finalised details on which communities will benefit from the North lot contract will be available. The R100 programme is a superfast broadband programme and so all connections delivered via the R100 contracts, our Scottish Broadband Voucher Scheme or commercial coverage will provide speeds of at least 30 Mbps.
R100 set out to ensure that everyone could access at least superfast speeds (30 Megabits per second) and so delivery of such a high proportion of full fibre (FTTP) technology is delivering more than our original commitment. As outlined in my response to S5W-30420, we have issued BT with an updated intervention area taking account of changes in commercial roll-out plans and so we expect that this FTTC figure will change once roll-out plans are finalised.
Once this remodelling work is finalised details on which communities will benefit from the North lot contract will be available. The R100 programme is a superfast broadband programme and so all connections delivered via the R100 contracts, our Scottish Broadband Voucher Scheme or commercial coverage will provide speeds of at least 30 Mbps.