Parliament Workbench
Data: Motions & questions to 3 Dec 2026

Written Question · S5W-32863 · Session 5

Further to the answer to question S5W-26101 by Paul Wheelhouse on 14 November 2019, what estimate it has made of the total cost to public f…

Answered Asked by David Stewart Lab Lodged 27 Oct 2020

The question

To ask the Scottish Government, further to the answer to question S5W-26101 by Paul Wheelhouse on 14 November 2019, what estimate it has made of the total cost to public funds of its handling of Pentland Ferries’ unresolved complaint to the European Commission.

The answer

Answered by Paul Wheelhouse on 18 Nov 2020 · 22 days after it was lodged, 7 days after it was due

Scottish Government Directorates do not routinely record separately how much staff time and resources they have allocated to individual tasks, and it is therefore not possible to accurately calculate the cost of dealing with Pentland Ferries’ complaints in the way the member has requested.
The European Commission has confirmed that it does not require the Scottish Government to provide any further information in relation to the complaint.

In the Official Report

No contribution in the Official Report cites S5W-32863 by reference.