Written Question · S5W-32696 · Session 5
Further to the answer to question S5W-27751 by Fiona Hyslop on 16 March 2020, whether the funding for Creative Communities is still £900,00…
The question
To ask the Scottish Government, further to the answer to question S5W-27751 by Fiona Hyslop on 16 March 2020, whether the funding for Creative Communities is still £900,000 for the period October 2020 to June 2021.
The answer
The Scottish Government has provided total funding of £900,000 to the Creative Communities Programme to cover the period to July 2021.
In the Official Report
No contribution in the Official Report cites S5W-32696 by reference.