Inspired Question · S5W-31968 · Session 5
Whether it will provide an update on the works at Wards 2A/2B at the Queen Elizabeth University Hospital and Royal Hospital for Children.
The question
To ask the Scottish Government whether it will provide an update on the works at Wards 2A/2B at the Queen Elizabeth University Hospital and Royal Hospital for Children.
The answer
Work on site has been progressing, although this has necessarily had to accommodate the fact that the hospital has remained operational during the COVID-19 pandemic. However, there have been significant delays as a result of COVID-19. This has included significant challenges with supply chains and the continued effects of social distancing during construction works.
We are still awaiting the finalised programme of works but NHS Greater Glasgow and Clyde are expecting work to be complete in May 2021.
NHS Greater Glasgow and Clyde are treating this with the upmost priority and I expect them only to open wards 2A/2B when the Board and the Scottish Government are assured the new systems have been commissioned and validated in line with guidance and Infection Control are supportive of service commencement.
We are still awaiting the finalised programme of works but NHS Greater Glasgow and Clyde are expecting work to be complete in May 2021.
NHS Greater Glasgow and Clyde are treating this with the upmost priority and I expect them only to open wards 2A/2B when the Board and the Scottish Government are assured the new systems have been commissioned and validated in line with guidance and Infection Control are supportive of service commencement.