Further to the answer to question S5W-29650 by Roseanna Cunningham on 11 June 2020, whether it will provide an update on whether, in light …

Answered Asked by Jackie Baillie Lab Lodged 21 Sep 2020

The question

To ask the Scottish Government, further to the answer to question S5W-29650 by Roseanna Cunningham on 11 June 2020, whether it will provide an update on whether, in light of the COVID-19 pandemic, Scottish Water has offered to pay contractors that are unable to continue delivery of work on capital investment and maintenance programmes.

The answer

Answered by Roseanna Cunningham on 30 Oct 2020 · 39 days after it was lodged, 3 days after it was due

Contractors working on Scottish Water’s capital programme were unable to work from 23 March 2020 until the end of May in line with lockdown guidance. Since the end of May Scottish Water’s capital programme has been remobilised and most projects are now back underway. Payments to contractors have been made in line with the entitlement set out within Scottish Water’s contracts. It uses the construction industry standard Engineering and Construct Contract (NEC) suite of contracts. This includes appropriate mechanisms to pay for allowable costs incurred during the period of lockdown
- for example the retention of site security, accommodation, etc… It should be noted that a significant element of Scottish Water’s supply chain staff were put onto the UK Government’s Job Retention Scheme which mitigated staff and labour costs being a cost to Scottish Water during lockdown. Scottish Water’s contract mechanisms allow for appropriate payments to be made for remobilisation and to cover the additional costs of new safe ways of working adopted in line with COVID-19 guidance.