Further to the answer to question S5W-29736 by Clare Haughey on 18 June 2020, what the timeline is for the application process for the new …

Answered Asked by Miles Briggs Con Lodged 17 Sep 2020

The question

To ask the Scottish Government, further to the answer to question S5W-29736 by Clare Haughey on 18 June 2020, what the timeline is for the application process for the new Managed Clinical Network for National Child and Adolescent Learning Disability Services, and what progress has been made with the development of this process.

The answer

Answered by Clare Haughey on 2 Oct 2020 · 15 days after it was lodged, on time

I refer the member to the answer to question S5W-30228 on 22 July 2020. All answers to written parliamentary questions are available on the Parliament's website, the search facility for which can be found at:
http://www.parliament.scot/parliamentarybusiness/28877.aspx .
As outlined to the member in the answer to question S5W-30228 Scottish Government officials are currently working to identify, a project lead and Lead Clinician to establish a Steering Group and develop the specification and standards for a National Leading Disability CAMHS Clinical Network. Subject to progress and the recommendations of the Steering Group, an application to the NHS National Specialist Services Committee for National MCN designation will follow.
I would like to reassure the member that although the pandemic has slowed the pace of this work, this is an important area of work and identifying a project lead will be progressed in the coming weeks.

In the Official Report

No contribution in the Official Report cites S5W-31878 by reference.