Written Question · S5W-31780 · Session 5
Further to its answer to question S5W-28699 by Humza Yousaf on 11 May 2020, whether it will provide an update on the progress towards build…
The question
To ask the Scottish Government, further to its answer to question S5W-28699 by Humza Yousaf on 11 May 2020, whether it will provide an update on the progress towards building all elements of the new women’s prison estate.
The answer
I have asked Teresa Medhurst, Interim Chief Executive of the Scottish Prison Service (SPS), to respond. Her response is as follows:
In line with Scottish Government guidance, work on the construction of the new Women’s National Facility and the Community Custody Units was temporarily suspended in March 2020 due to COVID-19.
Following the easing of restrictions, construction of the Women’s National Facility recommenced in June. Site preparation work continues for both Community Custody Units, with construction expected to commence in October.
Throughout the lockdown period, the SPS continued to work with both contractors on design elements and statutory applications in order to minimise the impact on the construction timeline as much as possible.
The SPS is working closely with the contractors to regularly assess timescales and this will continue as we progress through the phases of the Construction re-start Model and the impact beyond the lock-down phases becomes more apparent.
At this time, we anticipate that the construction of the CCUs will be completed early in 2022 and in Spring 2022 for the Women’s National Facility.
In line with Scottish Government guidance, work on the construction of the new Women’s National Facility and the Community Custody Units was temporarily suspended in March 2020 due to COVID-19.
Following the easing of restrictions, construction of the Women’s National Facility recommenced in June. Site preparation work continues for both Community Custody Units, with construction expected to commence in October.
Throughout the lockdown period, the SPS continued to work with both contractors on design elements and statutory applications in order to minimise the impact on the construction timeline as much as possible.
The SPS is working closely with the contractors to regularly assess timescales and this will continue as we progress through the phases of the Construction re-start Model and the impact beyond the lock-down phases becomes more apparent.
At this time, we anticipate that the construction of the CCUs will be completed early in 2022 and in Spring 2022 for the Women’s National Facility.
In the Official Report
No contribution in the Official Report cites S5W-31780 by reference.