Further to the answer to question S5W-27776 by Roseanna Cunningham on 12 March 2020, for what reasons supply chain development statements a…

Answered Asked by Lewis Macdonald Lab Lodged 9 Jul 2020

The question

To ask the Scottish Government, further to the answer to question S5W-27776 by Roseanna Cunningham on 12 March 2020, for what reasons supply chain development statements are not included in Crown Estate Scotland’s scoring process for applications under the ScotWind Leasing programme.

The answer

Answered by Roseanna Cunningham on 30 Jul 2020 · 21 days after it was lodged, on time

Such a step would be in contravention of conditions for Scotwind leasing which is designed to be compliant with State aid, procurement and competition regulations.