Further to the answer to question S5W-27298 by Clare Haughey on 4 March 2020, by what date ISD will complete this work.

Answered Asked by Alex Cole-Hamilton LD Lodged 5 Mar 2020

The question

To ask the Scottish Government, further to the answer to question S5W-27298 by Clare Haughey on 4 March 2020, by what date ISD will complete this work.

The answer

Answered by Clare Haughey on 19 Mar 2020 · 14 days after it was lodged, on time

As some Boards will need to replace or significantly enhance their systems, it is likely to be at least 1 year before the minimum dataset can be delivered and up to 3 years before the full core dataset will be available nationally.
ISD are supporting Boards to collect and submit the data, including liaison with system suppliers and locally based ISD analysts.