What the process is for planning appeals to be considered where a large-scale wind turbine has been refused planning permission at a local …

Answered Asked by Finlay Carson Con Lodged 13 Feb 2020

The question

To ask the Scottish Government what the process is for planning appeals to be considered where a large-scale wind turbine has been refused planning permission at a local authority level.

The answer

Answered by Kevin Stewart on 26 Feb 2020 · 13 days after it was lodged, on time

Any proposal to construct or operate a power generation scheme with a capacity under the threshold of 50 megawatts are made to the relevant local planning authority and require planning permission under the Town and Country Planning (Scotland) Act 1997. Proposed developments over 50 megawatts are dealt with under the Electricity Act and the final decision is made by Scottish Ministers. An examination by a reporter from DPEA will normally take place only when the local planning authority object to the proposed development.
Where an application for a proposal under 50 megawatts has been made to the council but the person who made the application doesn't agree with the decision, or the council hasn't made a decision, an appeal can be made to Scottish Ministers in certain instances.
In keeping with the vast majority of appeals a Scottish Government Reporter is appointed to make a determination on Ministers behalf. The Town and Country Planning Scotland Act 1997 sets out that the appointed reporter must make their decision in accordance with the development plan unless material considerations indicate otherwise. The reporter will consider the status of the plan, any emerging policies that may be relevant, and all the evidence submitted by parties involved in an appeal, and make their decision on the planning merits of the case. The reporter will decide what information they require to decide the appeal and whether this can be obtained by way of written submissions or whether a hearing or inquiry session is necessary. In all cases of this type the reporter will carry out an inspection of the site.

In the Official Report