Further to the answer to question S5W-26660 by Michael Matheson on 19 December 2019, when work on the installation of the sensors will (a) …

Answered Asked by Miles Briggs Con Lodged 21 Jan 2020

The question

To ask the Scottish Government, further to the answer to question S5W-26660 by Michael Matheson on 19 December 2019, when work on the installation of the sensors will (a) commence and (b) be completed, and how much this will cost.

The answer

Answered by Michael Matheson on 10 Feb 2020 · 20 days after it was lodged, 6 days after it was due

The safety of road users is our number one priority.
The procurement process for installation of the ice sensors and ancillary equipment is currently underway and we hope to be in a position to award the contract shortly, after which the sensors will be installed as soon as possible. Costings will be confirmed following completion of the procurement process.
In the meantime, robust procedures are in place to deal with issues relating to ice accumulation.

In the Official Report