Written Question · S5W-26976 · Session 5
Further to the statement by the Minister for Energy, Connectivity and the Islands on 9 January 2020 (Official Report, c. 39), what impact t…
The question
To ask the Scottish Government, further to the statement by the Minister for Energy, Connectivity and the Islands on 9 January 2020 (Official Report, c. 39), what impact the voucher scheme will have on the completion date of the R100 programme.
The answer
As I announced to Parliament on 9 January, it is expected that the majority of build for both the £83 million Central lot and £133 million South lot will be complete by the end of 2023, with timescales for the North lot (of £384 million in value) dependent on the length and outcome of the current legal proceedings.
As I made clear in my statement and the subsequent responses I gave to Members’ questions, on its own, the main procurement contracts would be insufficient to deliver our commitment of 100% superfast broadband access by the end of 2021. This is why,
- we will provide additional support to ensure that everyone can access, as a minimum, superfast broadband services by the end of 2021 if they are either not included in the list of premises specified in the successful bid or, where included on the target list of premises, the R100 roll-out in their area will not reach them in that timescale.
To deliver against this, I confirmed to Parliament that any properties which are not targeted through the contracts, or will benefit through delivery after 2021, will be eligible for our new Scotland-wide, demand-led voucher scheme that will be launched later this year to distribute grants to eligible customers. This new voucher scheme will be funded by the Scottish Government and will be targeted at allowing people and businesses to obtain superfast broadband from other sources and across a range of technologies, thereby ensuring access for all premises within the agreed timescale.
As I made clear in my statement and the subsequent responses I gave to Members’ questions, on its own, the main procurement contracts would be insufficient to deliver our commitment of 100% superfast broadband access by the end of 2021. This is why,
- we will provide additional support to ensure that everyone can access, as a minimum, superfast broadband services by the end of 2021 if they are either not included in the list of premises specified in the successful bid or, where included on the target list of premises, the R100 roll-out in their area will not reach them in that timescale.
To deliver against this, I confirmed to Parliament that any properties which are not targeted through the contracts, or will benefit through delivery after 2021, will be eligible for our new Scotland-wide, demand-led voucher scheme that will be launched later this year to distribute grants to eligible customers. This new voucher scheme will be funded by the Scottish Government and will be targeted at allowing people and businesses to obtain superfast broadband from other sources and across a range of technologies, thereby ensuring access for all premises within the agreed timescale.
In the Official Report
No contribution in the Official Report cites S5W-26976 by reference.