Written Question · S5W-26898 · Session 5
Further to the answer to question S5W-26535 by Roseanna Cunningham on 9 December 2019, what the estimated expenditure is to complete (a) th…
The question
To ask the Scottish Government, further to the answer to question S5W-26535 by Roseanna Cunningham on 9 December 2019, what the estimated expenditure is to complete (a) the Amlaird and Corsehouse strategic mains project from the September 2019 date referred to and (b) phase three of the wider Ayrshire Resilience Scheme.
The answer
The estimated expenditure to complete the Amlaird and Corsehouse strategic mains project from September 2019 is £0.7m. The estimated expenditure to complete phase three of the wider Ayrshire Resilience Scheme is £69m-£83m.
In the Official Report
No contribution in the Official Report cites S5W-26898 by reference.