The question

To ask the Scottish Government, further to the answer to question S5W-26535 by Roseanna Cunningham on 9 December 2019, what the estimated expenditure is to complete (a) the Amlaird and Corsehouse strategic mains project from the September 2019 date referred to and (b) phase three of the wider Ayrshire Resilience Scheme.

The answer

Answered by Roseanna Cunningham on 16 Jan 2020 · 8 days after it was lodged, on time

The estimated expenditure to complete the Amlaird and Corsehouse strategic mains project from September 2019 is £0.7m. The estimated expenditure to complete phase three of the wider Ayrshire Resilience Scheme is £69m-£83m.