Written Question · S5W-26792 · Session 5

Further to the answer to question S5W-26766 by Paul Wheelhouse on 19 December 2019, in light of the contracts for lots 2 and 3 of the R100 …

Answered Asked by Finlay Carson Con Lodged 19 Dec 2019

The question

To ask the Scottish Government, further to the answer to question S5W-26766 by Paul Wheelhouse on 19 December 2019, in light of the contracts for lots 2 and 3 of the R100 being signed, by what date it will publish detailed roll-out timetables for each.

The answer

Answered by Paul Wheelhouse on 16 Jan 2020 · 28 days after it was lodged, on time

My statement to Parliament on Thursday 9 January set out the details which are currently available for the roll-out of the contracts for lots 2 and 3 of R100.
In the case of the South lot, covering the entirety of Dumfries and Galloway, some 26,000 premises across the local authority areas within the lot area were identified for the contract and I am pleased to say that the successful bid from BT will deliver a fibre-to-the-premises (FTTP) solution for 99.2% of those premises, with a residual of in the region of 200 premises requiring an alternative solution through our aligned intervention; delivered through grant funding via a voucher to ensure a service of at least superfast speeds can be accessed.
As I explained in the Chamber, BT is currently updating its own modelling to reflect changes in commercial delivery and ,once this is complete and detailed survey work has been undertaken, I have committed to share specific details of the roll-out plans, down to premises level, and this information will ultimately be made available to the public through a proposed on-line checker.