The question

To ask the Scottish Government how many pieces of equipment at the Royal Hospital for Sick Children in Edinburgh were classified as outdated in July 2019; how many of these items are no longer in use; how much has subsequently been spent on maintaining and prolonging the working-life of the remaining items; how often the condition of these items are reviewed, and what plans it has to replace them.

The answer

Answered by Jeane Freeman on 3 Dec 2019 · 11 days after it was lodged, on time

NHS Lothian has a process for the maintenance and management of medical equipment, which was unchanged by the delayed move of the Royal Hospital for Sick Children (RHSC) in July 2019. Regular planned preventative maintenance and testing in accordance with manufacturers’ recommendations continues to take place on all medical equipment. When equipment falls out of manufacturer support or beyond economic repair a risk assessment is carried out with the users and, where necessary, replacement is arranged.
NHS Lothian have confirmed of the approximately 180 items on the medical physics database for RHSC that could be regarded as ‘outdated’ in July 2019, over 90% remains fit for use. Where possible, replacement has been managed through transfer of new items in the new Royal Hospital for Children and Young People (RHCYP) to the existing site, so there has been no additional purchase cost and no additional maintenance cost as the new items are under warranty. An example of this is the moving and commissioning of new anaesthetic machines from RHCYP in November to replace units for which manufacturer support had expired.
Where new equipment has had to be bought for RHSC since July 2019, this will be utilised elsewhere in NHS Lothian if it is not required for RHSC after migration to the new site.
- Due to the age of the operating theatre lights in RHSC, and the remaining manufacturer maintenance arrangement expiring in 2020, NHS Lothian are replacing these in February 2020. The cost across four theatres is approximately £90k, and once RHSC at Sciennes is decommissioned these lights will be transferred elsewhere in NHS Lothian.
- Rather than transfer x-ray equipment that had already been moved to RHCYP in anticipation of opening back to RHSC again, the manufacturer provided new kit free of charge, with NHS Lothian paying installations costs of £20k. The manufacturer will work with NHS Lothian to relocate and recycle this kit where it is needed in the future, in NHS Lothian or elsewhere.
- Replacement parts for the CT scanner at RHSC, costing £76k, will be returned to the supplier for credit when no longer in use at RHSC.
NHS Lothian have also used equipment bought for the new hospital that has now been put into use in the existing site includes 28 patient trolleys, 3 wheelchairs, 6 drip stands a treadmill and a range of domestic service equipment, e.g. vacuum cleaners and scrubbing machines.
NHS Lothian will continuously assess requirements for new equipment and furniture in RHSC and, where possible, items bought for the new facility will be put into use and then transferred when migration to the new site is complete.