The question

To ask the Scottish Government when it will announce the levels of funding for the next phase of the Learning Estate Investment Programme, and what the timescale will be for local authorities to bid for this.

The answer

Answered by John Swinney on 30 Oct 2019 · 14 days after it was lodged, on time

The next phase of projects to benefit from the £1 billion Learning Estate Investment Programme will be announced within 12 months.
The Scottish Government look forward to continuing discussions will local authorities in the coming months regarding which of their projects may be suitable for support through the Learning Estate Investment Programme.