Parliament Workbench
Data: Motions & questions to 19 Nov 2026

Written Question · S5W-25824 · Session 5

 whether sensors have been fitted to the Queensferry Crossing to alert engineers to the hazard of ice building up on its cables, with risk …

Answered Asked by Murdo Fraser Con Lodged 11 Oct 2019

The question

To ask the Scottish Government whether sensors have been fitted to the Queensferry Crossing to alert engineers to the hazard of ice building up on its cables, with risk of it falling on to the carriageways.

The answer

Answered by Michael Matheson on 30 Oct 2019 · 19 days after it was lodged, on time

The issues with ice are thought to be a result of a very specific set of weather conditions arriving in March 2019. Since then, processes have been developed to ensure that any ice formation is monitored and managed to minimise the impact on traffic over the structure.
Sensors which detect ice accumulation will be fitted to the bridge and incorporated in the structural health monitoring system.
The conditions that can lead to a build-up of ice of this kind are very rare in the Forth estuary.

In the Official Report

No contribution in the Official Report cites S5W-25824 by reference.