Inspired Question · S5W-25543 · Session 5
Whether it will provide a breakdown of the £16 million referenced in the Cabinet Secretary for Health and Sport's ministerial statement on …
The question
To ask the Scottish Government whether it will provide a breakdown of the £16 million referenced in the Cabinet Secretary for Health and Sport's ministerial statement on 11 September 2019 regarding the Royal Hospital for Children and Young People.
The answer
The estimated additional costs relating to the RHCYP project are as follows. These estimates will be refined as plans are further developed. As noted in my statement to Parliament on 11 September, I will keep members updated on costs as work proceeds on resolving the current situation.
Description
£000s
Costs associated with new hospital
Rectification for critical care and Haematology / Oncology
4,000
Contingency for further remedial action
2,000
6,000
Costs of maintaining existing sites
Dual running of existing sites
1,500
Additional Maintenance at current RHSC / DCN
2,000
Additional investments in current RHSC and DCN facilities and equipment post July 19 delay (estimate)
3,700
7,200
Project Team costs
Project Team Costs
1,500
Additional project support
550
Advisor Fees (legal, technical, financial)
300
2,350
Independent reviews
500
Total estimated additional costs
16,050
Description
£000s
Costs associated with new hospital
Rectification for critical care and Haematology / Oncology
4,000
Contingency for further remedial action
2,000
6,000
Costs of maintaining existing sites
Dual running of existing sites
1,500
Additional Maintenance at current RHSC / DCN
2,000
Additional investments in current RHSC and DCN facilities and equipment post July 19 delay (estimate)
3,700
7,200
Project Team costs
Project Team Costs
1,500
Additional project support
550
Advisor Fees (legal, technical, financial)
300
2,350
Independent reviews
500
Total estimated additional costs
16,050