Written Question · S5W-25522 · Session 5

To what extent the network capacity pinch points on the Highland Mainline, which restrict freight operators to 20 containers rather than th…

Answered Asked by John Finnie Green Lodged 26 Sep 2019

The question

To ask the Scottish Government to what extent the network capacity pinch points on the Highland Mainline, which restrict freight operators to 20 containers rather than the possible 28, impacts on its capacity to meet its climate change targets.

The answer

Answered by Michael Matheson on 11 Oct 2019 · 15 days after it was lodged, 1 day after it was due

With considered timetable adjustments longer freight trains could currently operate on the Highland Main Line. Going forward there is a requirement to balance timetabling and infrastructure interventions to support both increased freight and passenger services.
Recent trials of 28 container length freight trains on the Highland Main Line have been successful, and were in response to freight customer needs with work continuing on this project. Modal shift to rail freight is a key focus to help transport meet its overall Climate Change targets.