Written Question · S5W-23839 · Session 5
Further to the answer to question S5W-23068 by Paul Wheelhouse on 22 May 2019, whether it remains Transport Scotland’s plan to announce the…
The question
To ask the Scottish Government, further to the answer to question S5W-23068 by Paul Wheelhouse on 22 May 2019, whether it remains Transport Scotland’s plan to announce the 2019-27 Northern Isles Ferry Services' contract in August.
The answer
The timeline for the tender and delivery of the new contract is currently on schedule. Subject to the conclusion of the on-going Judicial Review appeal and associated complaint lodged with the European Commission, we anticipate that the outcome of the tender procedure for the Northern Isles Ferry Services will be announced in August 2019.