Further to the answer to question S5W-23072 by Shirley-Anne Somerville on 21 May 2019, what the latest date discussions with IBM regarding …

Answered Asked by Mark Griffin Lab Lodged 29 May 2019

The question

To ask the Scottish Government, further to the answer to question S5W-23072 by Shirley-Anne Somerville on 21 May 2019, what the latest date discussions with IBM regarding an extension must (a) begin and (b) conclude.

The answer

Answered by Shirley-Anne Somerville on 6 Jun 2019 · 8 days after it was lodged, on time

No formal dates for any discussions to begin and conclude have been agreed with IBM.
In order to extend the contract, the Scottish Government would need to give IBM at least one month’s notice prior to the initial end date. Any discussions would need to take place in sufficient time to support this deadline.

In the Official Report

No contribution in the Official Report cites S5W-23506 by reference.