To ask the Scottish Government, further to the answer to question S5O-03231 by Paul Wheelhouse on 15 May 2019 (Official Report, c. 11), whether it will provide an update on its revised projections for the total spend on vessels 801 and 802.
The answer
As confirmed on 15 May 2019 in the answer to question S5O-03231, Scottish Government has written to FMEL to request information relating to vessels 801 and 802, in order to support a detailed programme with key milestones to support a revised cost of completion for both vessels. Scottish Government has not yet received this information.