Written Question · S5W-21784 · Session 5
Further to the answer to question S5W-21273 by Michael Matheson on 19 February 2019, on what date the mandatory standstill commenced; how l…
The question
To ask the Scottish Government, further to the answer to question S5W-21273 by Michael Matheson on 19 February 2019, on what date the mandatory standstill commenced; how long it proceeded before a bidder raised queries; what its intended duration was, and for what reason the successful bidder was not named publicly at the commencement of the standstill period, in light of it naming successful bidders in other similar contracts.
The answer
As confirmed in my answer to question S5W-21273 on 19 February 2019, on conclusion of the procurement competition for the contract to construct the A77 Maybole Bypass, bidders were informed of our intention to award the contract. This marked the commencement of the mandatory minimum 10 day standstill period.
During this period queries were raised by one of the bidders and we are currently progressing to resolve these queries before the contract is awarded and the successful bidder announced.
In line with the legislation governing procurement of public contracts, it would not be appropriate for me to comment further at this time on any matters relating to the queries raised to avoid prejudicing the outcome of their resolution.
During this period queries were raised by one of the bidders and we are currently progressing to resolve these queries before the contract is awarded and the successful bidder announced.
In line with the legislation governing procurement of public contracts, it would not be appropriate for me to comment further at this time on any matters relating to the queries raised to avoid prejudicing the outcome of their resolution.
In the Official Report
No contribution in the Official Report cites S5W-21784 by reference.