Written Question · S5W-21672 · Session 5

Further to the answer to question S5W-20184 by Michael Matheson on 13 December 2018, when it will provide the information that was requeste…

Answered Asked by Colin Smyth Lab Lodged 13 Feb 2019

The question

To ask the Scottish Government, further to the answer to question S5W-20184 by Michael Matheson on 13 December 2018, when it will provide the information that was requested.

The answer

Answered by Michael Matheson on 8 Mar 2019 · 23 days after it was lodged, on time

In the first year of the ScotRail Franchise no Committed Obligation Payment Adjustments were incurred. The second year Transport Scotland received £875,219.14, reducing to £466,941.84 in the third year. The Committed Obligation Payment Adjustments in the current year to date is £1,002,770.84.
Committed Obligation Payment Adjustments in relation to the late delivery of Class 385 trains are not contained in these figures due to ongoing commercial sensitivities with ScotRail and their supply chain which is still subject to on-going contractual disputes.