How many ScotRail Service Quality Incentive Regime (SQUIRE) audits were carried out in 2018; how many failures were recorded, broken down b…

Answered Asked by John Finnie Green Lodged 22 Jan 2019

The question

To ask the Scottish Government how many ScotRail Service Quality Incentive Regime (SQUIRE) audits were carried out in 2018; how many failures were recorded, broken down by type of failure, and what the total financial penalty was.

The answer

Answered by Michael Matheson on 30 Jan 2019 · 8 days after it was lodged, on time

Transport Scotland team of six Inspectors audit all 354 ScotRail Stations and approximately 180-200 trains at least once every four weekly cycle. There are 13 rail periods per year.
The member will wish to be aware that information on SQUIRE audits, passes and fails during 2018, is available from the Scottish Parliament Information Centre (Bib. number 60425).
The variance of audit numbers is due to facilities being inspected either by asset, platform or station.
The total penalties attributed for SQUIRE performance during 2018 was £4.47m (including RPI).