Written Question · S5W-20818 · Session 5
Further to the answer to question S5T-01427 by Michael Matheson on 8 January 2019 (Official Report, c.4), whether it will publish the remed…
The question
To ask the Scottish Government, further to the answer to question S5T-01427 by Michael Matheson on 8 January 2019 (Official Report, c.4), whether it will publish the remedial action plan that it has agreed with ScotRail; how it will monitor the implementation of the plan, and by what date it will publish its assessment of its effectiveness.
The answer
Transport Scotland officials will consider publication of the remedial plan on receipt and agree a monitoring process with ScotRail to assess its performance and whether it is actually delivering on the plan that has been submitted. Until Transport Scotland has received and reviewed the detail of the plan a date cannot be committed for publishing an assessment into its effectiveness.
In the Official Report
No contribution in the Official Report cites S5W-20818 by reference.