Parliament Workbench
Data: Motions & questions to 26 Nov 2026

Written Question · S5W-20280 · Session 5

Further to the answer to question S5W-17823 by Michael Matheson on 10 August 2018, which stations that are (a) partially and (b) not access…

Answered Asked by Colin Smyth Lab Lodged 29 Nov 2018

The question

To ask the Scottish Government, further to the answer to question S5W-17823 by Michael Matheson on 10 August 2018, which stations that are (a) partially and (b) not accessible it (i) plans to improve access at, broken down by the date that this improvement work will (A) commence and (B) be completed and (ii) does not plan to improve access at, broken down by reason.

The answer

Answered by Michael Matheson on 14 Dec 2018 · 15 days after it was lodged, on time

A list showing the extent of accessibility at each of Scotland’s railway stations is available from the Scottish Parliament Information Centre (Bib number 60294).
The Scottish Government priority list of stations for the Access for All Programme, a reserved matter and funded by the UK Government, for rail control period 6 (CP6) (2019 to 2024), is currently being considered by the UK’s Department of Transport. The UK Government sets the criteria that determines which stations can be included in the Access for All Programme.
The remaining rail control period 5 (CP5) accessibility improvement projects, at Kilmarnock and Kilwinning, are due to be completed by December 2018 and March 2019 respectively.
Furthermore, the Scottish Government has committed to improve accessibility at; Aviemore, Pitlochry, Livingston South, Cleland, Addiewell and Fauldhouse during CP6.
It is the policy of Scottish Ministers to have all rail matters, including accessibility, fully devolved to the Scottish Government. We will always look to improve accessibility as part of our wider rail investments and intend to make all stations fully accessible .

In the Official Report

No contribution in the Official Report cites S5W-20280 by reference.